BB&T Ballpark Construction Update for October 25

Charlotte, NC – The construction of BB&T Ballpark — the future home of the Charlotte Knights, continues to progress.

- Recently, crews removed a crape myrtle tree from the site (photos attached). The tree, which was originally planted at the site in February of 1998, was re-planted in the median of the 6400 block of Old Reid Rd (about 30 feet from the intersection of Archdale Rd).

 

- Demolition of the Virginia Paper Company Building was completed last week. Work on the building began on Tuesday, October 2.

 

- 4th Street roadwork continues, as well as mass excavation.

 

The entire construction process can be viewed 24 hours a day, seven days a week through the BB&T Ballpark webcam. Here is a link to view the webcam: http://bit.ly/SFyZuP

 

Media members interested in more information or interested in gaining video/photography footage of the site, are asked to contact Tommy Viola by phone at 704-357-8071 ext. 2116 or by email at tommyv@charlotteknights.com.